The Havre des Pas roadworks will take longer than planned.
Asphalt can't be supplied because of technical issues at the Ronez manufacturing plant.
The main resurfacing part of the work has been paused until the problems with the plant are fixed.
The work started on 10 January and was due to take seven weeks to complete.

A government spokesperson says the road will stay closed for safety reasons - and the site team is working on contingency plans to limit delays and the impact they have.
Questions were asked of the Infrastructure Minister in the States Assembly last week about how to mitigate the disruption caused by the work.
Deputy Kevin Lewis said his officers were talking to the contractor every day to make sure it is done as soon as possible.

Deadline set to bring forward Jersey's whistleblowing law
Tonight's Sanctuary Trust Sleep-out marks 15 years of its homelessness support
Microsoft suffers global outage - as fix not going 'as expected'
David Walliams’ books to remain available in Jersey Library and schools
One in three homeless people in work
Fort Regent vision 'was never matched' by a budget that could deliver it, says JHA
Buzzing! Bears and Bees coming to Jersey
JCG Year 7 Choir learn and perform wartime song